Ministry of Transportation / Ministère des Transports
Home
HOME > Publications > OPS > CDED Special Provisions Archives Volumes

Environmental Standards and Practices

AMENDMENT TO MTO GENERAL CONDITIONS OF CONTRACT, APRIL 2004


October 2004


Construction Schedule

Clause GC7.01.07, Critical Path Schedule, and Clause GC7.01.08, Construction Staging, are deleted and replaced by the following:

The Contractor shall prepare, and update as required, a construction schedule indicating the timing of the major and critical activities of the Work. The schedule shall be designed to ensure conformity with the specified Contract Time. The schedule shall be submitted to the Contract Administrator within fourteen (14) days from the date of the contract award.



NOTES TO DESIGNER

Clause GC7.01.08, Construction Staging cannot be retained if Clause GC7.01.07, Critical Path Schedule is deleted. In general, this Special Provision is only to be used in contracts that do not include SP199S53.